Background 

The project involved the construction of two hotel towers, Ibis Hotel and the Novotel Hotel. Both towers comprise of four basement car parking levels, a ground floor, two podium levels that will house restaurants, two mezzanine floors and 20 additional floors offering 518 rooms. Amenities in the project include a swimming pool, a gymnasium, restaurants, a health club, a spa, a jacuzzi and 24-hour security.

 

Services

Irinatech offered a comprehensive MEP project management consultancy, engineering and designing services package to all aspects of the MEP execution elements.

 

Our core responsibility was to provide support to the main contractor in the planning, engineering, procurement, project management implementation and site supervision of such directives with a dynamic resource team.

 

Our role was to assist, support and co-ordinate between the main contractor and all specialist subcontractors with all interrelated civil, architectural and interior design works to complete a prestigious hotel project.

 

In addition Irinatech provided full guidance to correct contractual documentation procedures and correspondences including close-out documentation to all aspects of the project life cycle and stakeholders.

 

Other KPIs are to advise the client on a daily, weekly and monthly basis of all types of risk and uncertainties including contractual, financial, safety risks, liaison with all authorities, QA/QC, testing and commissioning and project closure procedure and documentation.

 

Projects Details

  • Location:

    Abu Dhabi, UAE
  • PM/CM

    Irinatech
  • Consultant

    Arab Engineering Bureau
  • Contractor

    Catic
  • Sector

    Hotel & Leisure
  • Scope

    Project construction, procurement and design management
30 YEARS OF EXCELLENCE